What is CDM in Construction? A Guide to the CDM Regulations
CDM stands for the Construction (Design and Management) Regulations 2015, the main set of regulations governing health, safety and welfare on UK construction projects.
CDM applies to every construction project, from domestic extensions through to major commercial developments, and sets out who is responsible for managing risk at each stage of a build, from design through to completion.
Who are the duty holders under CDM?
CDM identifies specific roles, each with legal responsibilities:
- Client: the organisation or individual for whom the project is carried out. Clients must make suitable arrangements for managing a project, including appointing the right people and allowing sufficient time and resources.
- Principal designer: appointed on projects with more than one contractor, responsible for planning, managing and monitoring the pre-construction phase, including identifying and eliminating foreseeable risks at the design stage.
- Principal contractor: responsible for planning, managing and monitoring the construction phase, including coordinating health and safety matters between contractors on site.
- Designers: anyone preparing or modifying a design must take account of health and safety risks their design may create.
- Contractors: responsible for managing the health and safety of their own work and cooperating with others on site.
On smaller, single-contractor projects, some of these roles are consolidated, but the underlying duty to manage risk doesn’t disappear.
What does CDM actually require in practice?
Depending on the project, CDM typically requires:
- Pre-construction information: relevant health and safety information shared with the project team before work starts.
- A construction phase plan: setting out how health and safety will be managed during the build.
- A health and safety file: a record of information needed for any future construction, maintenance or demolition work, handed to the client at project completion.
When does a project need to be notified to the HSE?
A construction project is notifiable to the HSE if either of the following applies:
- It’s expected to last longer than 30 working days and have more than 20 workers on site at the same time at any point, or
- The total amount of construction work adds up to more than 500 “person days.” A person day simply means one person working on site for one day. So 500 person days could be 10 people working on site for 50 days, 50 people working for 10 days, or any other combination that adds up to the same total. This threshold exists to catch smaller, longer-running projects that don’t meet the first test but still involve a significant amount of work overall.
What is an F10 notification?
An F10 is the specific form used to notify the HSE that a construction project meets the notifiable thresholds above. It’s not a request for permission — the project doesn’t need HSE approval to go ahead — it’s simply a legal requirement to tell the HSE a notifiable project is happening, so they have visibility of construction activity and can target inspections where needed.
The F10 must be submitted by the client using the HSE’s online notification form, and it must be submitted before construction work begins on site. It typically asks for details including:
- The project address and a brief description of the work
- The client, principal designer and principal contractor details
- Planned start date and expected duration
- The estimated maximum number of workers on site at any one time
If project details change significantly after submission, for example, a different principal contractor is appointed, or the timeline shifts substantially, an updated F10 should be submitted to keep the HSE’s record accurate. Notifiable projects require an F10 notification to be submitted to the HSE before work begins.
What happens if CDM isn’t followed?
Non-compliance with CDM is a common factor in serious construction accidents, and the HSE actively inspects and enforces against it — including issuing improvement or prohibition notices, and prosecution in serious cases. Given construction consistently ranks among the highest-risk sectors for workplace injury, CDM compliance isn’t a paperwork exercise; it’s directly tied to preventing serious harm on site.
How SMC Safety Solutions can help
We can support you with understanding which CDM duties apply to your specific project and making sure the right documentation, from pre-construction information to the construction phase plan, is actually in place is where.
As part of our health and safety consultancy services, we provide CDM consultancy and compliance support, including principal designer and principal contractor support, site audits and method statements, for construction businesses across London, Essex, Kent, Suffolk and Cambridgeshire.
FAQs
What does CDM stand for?
CDM stands for the Construction (Design and Management) Regulations 2015. They are UK regulations that set out how health, safety and welfare must be managed throughout a construction project, from design through to completion.
When does a construction project need to be notified to the HSE under CDM?
A project is notifiable if it’s expected to last longer than 30 working days and have more than 20 workers on site at any one time, or if it exceeds 500 person-days of work, requiring an F10 notification before work begins.